Losing millions of dollars a year at its power plants, Ohio-based FirstEnergy has asked the Trump administration for help. Though it may have the president’s ear, it’s unclear how much President Trump can do to help the company’s struggling coal and nuclear plants.
FirstEnergy, which filed for bankruptcy last month, and plans to close three nuclear plants in Pennsylvania and Ohio, wants Energy Secretary Rick Perry to declare a “202-C” grid emergency, and make customers in Pennsylvania and surrounding states pay more for electricity from nuclear and coal.
Otherwise, it says more plants will close.
Trump, at a recent tax roundtable in West Virginia, said of FirstEnergy’s request: “We’ll be looking at that. We’re tryin’.”
The night before, Trump had reportedly attended a fundraiser with a FirstEnergy lobbyist, Jeff Miller, though the company would not confirm that.
What is a 202? It’s a provision of federal law designed to keep the grid functioning during extreme events that could cause power outages, said Ari Peskoe, an electricity law professor at Harvard.
“It was specifically written by Congress in 1935 to ensure that electricity supply did not have the sort of problems that arose during World War One,” Peskoe said.
The Department of Energy has used the law only eight times since 2000. It’s been used to keep plants running after hurricanes Katrina and Ike, and when a lightning strike knocked out a power plant last year.
What’s the emergency this time? Peskoe says that’s the problem.
“What FirstEnergy is describing in its application is not an emergency. It’s just that they’re not getting paid as much as they’d like. That’s not an emergency.”
What’s more, it’s requesting economic relief for its power plants over a period of four years.
“I think that they’re really, really stretching it,” said Sam Walsh, a former deputy general counsel for energy policy at the Department of Energy during the Obama administration.
“That is a very, very broad action that they’re asking D.O.E. to take.”
FirstEnergy has argued that without a 202-c, PJM Interconnection, the power grid that covers the mid-Atlantic, could face blackouts during times of peak demand, as coal and nuclear plants continue to close.
“Nuclear and coal-fired generators in PJM have been closing at a rapid rate — putting PJM’s system resiliency at risk — and many more closures have been announced,” the company wrote, in its request letter to Perry. An agency spokeswoman said the request is “under review.”