Energy storage saves Arizona utility from building 20 miles of transmission, distribution lines
The two, 4 MWh Advancion batteries are made by AES Energy Storage. Construction on the project is slated to begin in fall 2017. Image: APS
Arizona Public Service (APS) announced Wednesday that rather than rebuild miles of electricity transmission lines, it will install two battery storage systems totalling 8MWh in rural Punkin Center, Arizona — making it one of the first electricity companies in the US to utilise batteries instead of traditional infrastructure.
The two, 4 MWh Advancion batteries are made by AES Energy Storage. Construction on the project is slated to begin in fall 2017. While the use of energy storage to replace or complement the role of traditional wires, cables and substations has long been talked about, with one New York project discussed a few years ago thought to provide an opportunity to save a network operator more than three-quarters of a billion Dollars in upgrades to a substation for utility Con Edison, there has been little in the way of traction since. At present most utility-scale storage systems are providing grid-balancing or renewables integration – or both – rather than being seen as an alternative to transmission and distribution (T&D) infrastructure spending.
Scott Bordenkircher, APS’s director of transmission and distribution technology innovation and integration, said: “This project is a crucial step in the right direction for Arizona’s energy future. Over the next 15 years, APS has plans to add 500MW of storage capacity. This project is indicative of the type of smart grid APS envisions for customers, one that enables people to have more technology in their own homes.”
Currently, APS is using batteries to store excess solar power for use after sunset, with the batteries storing energy to use at peak times and for other functions such as voltage support.