A previous post on this blog reported a complaint by an electric storage resource owner that FERC must reform a Regional Transmission Organization’s (RTO’s) tariff with respect to the treatment of storage batteries. In response, FERC issued an Order that requires the RTO to adopt rules that allow storage resources to participate in all of its markets and that account for those resources’ physical and operational characteristics. The Order is significant because it breaks down barriers to the participation of storage resources in energy, capacity and ancillary services markets in an RTO whose rules are shown to violate the policies proposed in FERC’s Storage NOPR.

The value of storage resources to the grid

The reliable operation of the North American alternating current (AC) grid depends on maintaining a frequency near 60 Hertz (Hz). If frequency deviates too far from 60 Hz, the grid can become unreliable. Batteries’ and flywheels’ unique ability to quickly absorb and discharge electricity provides them with significant operational flexibility to help keep the bulk power system in balance. Importantly, these electric storage devices can also provide a variety of additional services in bulk power markets.

The complaint and the Order

Indianapolis Power & Light (IPL) owns a grid-scale lithium ion battery-based energy storage system that, it claims, is capable of providing a variety of grid support services to the Midcontinent ISO (MISO). In its complaint, IPL argued that the MISO tariff limits storage resources to providing only one type of service (regulation service) but subject to a dispatch protocol developed for flywheels that is not appropriate for lithium ion batteries and other fast resources. More importantly, IPL’s battery facility is technically capable of providing services in addition to regulation. For example, the facility can act like a demand response resource and supply energy and other services in MISO’s markets. IPL asserted the tariff should allow any resource to provide the services it is technically capable of providing.

FERC agreed with IPL, finding that MISO’s tariff unnecessarily restricts competition by preventing storage resources from providing all the services they are technically capable of providing, which could lead to unjust and unreasonable rates. The Order says that “electric storage resources…should not be required to participate in MISO’s markets by using rules that were designed for other types of resources….because those participation models do not accommodate the unique features of electric storage technologies” and that “failure to recognize the unique physical and operational characteristics of electric storage resources could unnecessarily restrict competition by preventing electric storage resources from providing all the services that they are technically capable of providing, which could lead to unjust and unreasonable rates.”

The Order finds that IPL has met its burden to show that the MISO Tariff is unjust, unreasonable, and unduly discriminatory or preferential. Accordingly, FERC orders MISO “to remedy its unjust and unreasonable Tariff to provide Indianapolis Power with relief”…..