ISO New England files interconnect for 16 MW energy storage project in Maine RSS Feed

ISO New England files interconnect for 16 MW energy storage project in Maine

ISO New England and interconnecting transmission owner Central Maine Power on Dec. 19 filed with FERC an executed non-conforming Standard Small Generator Interconnection Agreement with FPL Energy Wyman for a 16 MW battery project at an existing power plant site in Maine.

The existing generating facilities where this project site is located make up the Wyman Station, which is a fossil generating facility comprised of Units 1, 2 and 3 in Yarmouth, Maine, and FPL Wyman IV’s William F. Wyman No. 4, a fossil generating facility also located there.