Energy Department Suspends Funding for Texas Carbon Capture Project, Igniting Debate RSS Feed

Energy Department Suspends Funding for Texas Carbon Capture Project, Igniting Debate

Energy Secretary Moniz pulls funds for the project from the FY2017 budget, as the DOE’s inspector general says the agency has been taking too much risk.

The Obama administration has suspended funding for a large, troubled carbon capture and storage project, a decision being challenged by politicians from both parties and environmental advocates alike.

While the Texas Clean Energy Project is not officially dead, continued refusal by the Department of Energy to extend any more money would effectively kill it, according to its builder. That would make it the fifth CCS project the DOE has backed away from.

The agency took a tough stand in February when it denied a request by the project’s developer, Summit Texas Clean Energy, for an $11 million advance from its pot of promised federal money. In its budget request for the fiscal year 2017, which begins October 1, the DOE asked Congress to strip the $240 million pledged to the project from the agency’s Clean Coal Initiative and use it for other research and development efforts instead. A final vote on the budget will come late this year.

In a world that continues to burn fossil fuels, CCS is seen as critical to avoid the most calamitous consequences of global warming.

The Clean Coal Initiative had already been under audit by the DOE’s inspector general’s office, which grew alarmed by how the agency had allowed the Texas project to drag on. The IG, an independent auditing office, issued a special report on it in April.

“Due to Summit’s inability to obtain the required commercial debt and equity project financing and the adverse effect of changing energy markets on the demand for coal-based power plants, we are concerned about the viability of the Project and the Department’s continued involvement,” the inspector general’s report said. “Although construction of the plant was originally planned for completion in June 2014, the Project remains in the project definition phase. Additionally, we found that the Department had taken actions that increased its financial risk in the Project.”

The Texas Clean Energy Project would capture 2 million tons of CO2 a year from a coal-gasification plant, or 90 percent of its annual emissions, and lock them deep underground.

The federal government has been by far the largest investor in the Texas Clean Energy Project.

The DOE committed $450 million, of which $116 million has been allocated. Unused portions of Recovery Act funds allocated to the project expired in September 2015, reducing the total funding to $346 million. In the past six years, the estimated costs of the project have soared from $1.98 billion to to $3.98 billion. Private investment, meanwhile, is $45 million in the development phase, according to official documents.

In its response to the audit, the department said it would not spend any additional money unless the company finalizes engineering and construction contracts, and secures debt and equity to cover the building costs by May 13. On Friday, the DOE said it had extended this deadline by seven weeks, a move that it said did not commit the agency to spending any more money.

A Texas-Sized Tug of War

Summit Texas Clean Energy and its backers in Congress—led by Texas Rep. Lamar Smith, chair of the House Committee on Science, Space, and Technology—said the move to cut funding came without warning, and they’re pushing back. In a project cost statement dated April 29, the company said, “We need the $11 [million] to complete our closing activities which include fixing a large portion of the EPC costs at current advantageous prices, and subsequently finalize the equity and debt.”

“TCEP is not stalled. It is advancing and still attracting private capital,” Jason Crew, chief executive of Summit Texas Clean Energy, said in a letter to Smith on April 29, urging his help in reversing the DOE’s decision.

“Withholding the $11 million is not a prudent step at this point in the development process. It is an action that…will very likely terminate the development process,” Crew wrote, “and assure the end of the project and loss of all public and private funds invested to date.”

Notably, a similar request came from a group of prominent environmental and clean energy advocates—the Clean Air Task Force, Natural Resources Defense Council, Great Plains Institute, Center for Climate and Energy Solutions and Third Way. In a letter to Energy Secretary Ernest Moniz on March 21, the groups singled out the Texas project as being a particularly important demonstration of CCS technology. The plant would be the first commercial-scale coal-fired power plant to capture such a high percentage of its CO2 emissions.

It would be “unfortunate if the project fails, both for the loss of the substantial taxpayer dollars already provided to the project and for the loss of an important opportunity to add a significant project employing a high level of carbon capture for power and chemical processes,” the letter said.

Another coaliton of groups—including Friends of the Earth, Taxpayers for Common Sense and the R Street Institute—took the opposite side. “Wasting our tax dollars on projects like the Texas boondoggle is not the answer to the climate crisis,” said Lukas Ross, climate and energy campaigner at Friends of the Earth, in a May 13 press release.

“Secretary Moniz needs to pull the plug before this false solution gets more of our money.”

The Texas congressional delegation wrote its own letter to Moniz on March 18, arguing that the DOE didn’t give fair warning of the decision to cut off federal dollars, and that denying the funds could threaten future partnerships between government and industry.

“We acknowledge that TCEP did not accelerate to the full-scale construction phase as quickly as DOE or Summit Power would have preferred…we believe DOE should reconsider its assessment of the project’s progress and release the requested $11 million in funding,” the lawmakers wrote.

House lawmakers grilled Moniz during a March 22 budget hearing, questioning the department’s rationale for defunding the project. Moniz said the funds were reallocated because the company missed many critical deadlines.

“No one questions the desirability of the project…That isn’t the issue,” he said, “but the program decided it was just time to move on and to invest in some new innovative technologies because of the lack of milestones being met.”

$1.1 Billion Worth of Projects Halted

Planned for construction 15 miles west of Odessa, Texas, the pre-combustion carbon capture project remains in the preliminary design phase. The idea is to extract CO2 from the coal and concentrate it into a gas that can be transported and stored before the rest is burned for fuel. It would generate 400 megawatts of electricity. The captured CO2 would be injected into old wells in the West Texas Permian Basin to stimulate more oil production, and then be stored permanently underground in the depleted oil-bearing formations.

The original funding agreement in 2010 capped federal spending at $15 million during the preliminary phase, but the DOE exceeded that limit by $101 million, according to the inspector general’s report. “As of February 2016, the Department had invested about $116 million in the Project without assurances that it would succeed,” it said.

Read full article at Inside Climate Change